Since January
this year Profile Techniques Ltd have embarked on an expansion
and improvement program.
January - The lease for Unit 11 secured pending
reparation work by the landlord. New offices and canteen facilities
built on the shop floor of Units 12/13.
February - Work started upgrading the electrical
switch gear and re routing power cables to enable a new reception
area to be built and eventually machinery on the shop floor to
be moved to allow for a greater working space.
March - New Boston Matthew's 60 mm Single screw
extruder and down stream equipment ordered along with new moving
punch unit.
April - Reception area completed.
May - Preparation work on unit 11 completed and
storage racking moved and erected.
June - Mezzanine floor erected in Unit 11 and
electrical improvements continue.
July - Power cable laid to Unit 11 and pipe work
started for water supply to new water cooling system.
August - Expansion continues. New extruder to
be commissioned by the end of the month.
|